Corroded sewer main along Texoma Parkway that overflowed seven times since September is up for a $410,000 emergency replacement

Sewer gas has eaten through a deep ductile iron main near US 75, city staff say. The council takes up an emergency contract with Hayes Construction on Nov. 16 to pipe-burst in a new line resistant to the gas.

Hugo Baptiste· AI-assisted, edited by Jake Team

November 9, 20262 min read

Civic Infrastructure Repair - illustration, Jake Team LLC

A sewer main buried more than 20 feet under North Texoma Parkway has collapsed in several places, and Sherman wants to replace it under an emergency contract worth $410,000.

The City Council will consider the repair as a consent item at its Nov. 16 meeting, according to the agenda posted Monday. The work would go to Hayes Construction, a Sherman company, and be paid from the city's 2026-27 Utility Improvement Fund.

What failed

The 14-inch line runs along the east side of North Texoma Parkway toward North Sam Rayburn Freeway. A staff report says hydrogen sulfide, the gas that builds up in sewers, has eroded the ductile iron pipe and caused multiple collapses between the south side of East Sycamore Street and the southern edge of the property at 1521 N. Texoma Parkway.

City crews reported seven sanitary sewer overflows to the Texas Commission on Environmental Quality from the manhole upstream of the damage between Sept. 7 and Oct. 22, when an emergency bypass pump was installed, the report says.

A requisition signed Oct. 12 by Public Works Director Eric Sandberg described a manhole in the 1500 block of Texoma Parkway that was actively overflowing onto the surrounding area and called it a public health emergency.

How it would be fixed

Because the main is so deep, staff say digging it up would be extremely difficult. Instead, the contractor would use pipe bursting, a trenchless method that breaks apart the old pipe while pulling a new one into its place. The replacement would be high-density polyethylene, which the report says stands up to hydrogen sulfide.

Hayes' Oct. 21 proposal lists about 780 feet of 18-inch HDPE pulled in by pipe bursting, roughly 310 feet of 15-inch pipe laid by open cut at a depth of 21 feet, one new manhole, connections to existing manholes, locating gas and fiber optic lines in the way, and a month of bypass pumping.

The company suggested the city budget a contingency of at least 15% for conditions it could find on the upstream end.

The same agenda includes a $447,453 engineering contract with Westwood Professional Services to design a wider Interurban Parkway between FM 1417 and Progress Drive, which the Sherman Economic Development Corp. would reimburse, and an update to the city's rules on fats, oil and grease that restaurants and other businesses send into the sewer system.

The council meets at 5 p.m. at City Hall, 220 W. Mulberry St.

Sources

shermantx.api.civicclerk.com

shermantx.api.civicclerk.com