Low bid of $115,441 would pay for storm drains to ease flooding at a Setting Suns low-water crossing

Hayes Construction of Sherman beat two other bidders for the Phase IV drainage work near Mohican Drive and South Cimmaron Trail. The City Council takes up the contract Monday.

Carmen Solis· AI-assisted, edited by Jake Team

November 15, 20262 min read

Civic drainage improvements - illustration, Jake Team LLC

A storm drain project meant to ease flooding at a low-water crossing in the Setting Suns subdivision is ready for a contractor, with the City Council set to award the work Monday.

Hayes Construction LLC of Sherman submitted the lowest of three bids, $115,441.50, for what the city calls the Phase IV Drainage Improvements for Setting Suns, according to the council packet. Drake General Contractors bid $132,650 and KDA Industries bid $178,208.25 when the bids were opened Oct. 23.

The contract is on the consent agenda for the council's 5 p.m. meeting at City Hall, 220 W. Mulberry St., which means it can be approved with other routine items in a single vote unless a council member or resident asks to pull it out. City staff recommends approval.

What gets built

The city's own engineering staff drew the plans, aimed at local flooding where Mohican Drive meets South Cimmaron Trail. Two wye inlets will catch runoff and send it through reinforced concrete pipe, about 84 feet of 15-inch pipe and 86 feet of 18-inch pipe in the bid sheet, to a new grass channel.

That channel will carry the water to an existing channel the city designed earlier.

The bid sheet also shows crews tearing out the concrete low-water crossing, removing and rebuilding part of South Cimmaron Trail with new base rock and asphalt, and patching gravel on Mohican Drive. Seven trees are on the removal list, including a 48-inch oak and a 30-inch elm.

Hayes' price includes a $15,000 general contingency and an allowance for lowering a water line if crews run into one.

Paid for with 2023 bonds

The money comes from certificates of obligation the city issued in 2023 for capital projects, the staff report says. The project carries capital improvement number 26-018.

Sherman advertised the job for bids in early October. If the council approves the contract, the resolution authorizes the city manager to sign the construction agreement; the packet does not list a start date or how long the work will take.

Sources

shermantx.api.civicclerk.com

shermantx.api.civicclerk.com

Advertisement

Share

Carmen Solis· AI-assisted, edited by Jake Team

Carmen Solis covers weather, the environment, and outdoor life around Sherman.

Related Stories

More in Texas