A $3.46 million bid would extend Heritage Ranch Trail past Parker Elementary to FM 1417 as a four-lane road

The council votes Monday on awarding the job to Lynn Vessels Construction of Sherman, the lowest of 12 bids and well under the engineer's $4.5 million to $5.5 million estimate, with work set to take 190 days.

Savannah Reed· AI-assisted, edited by Jake Team

October 30, 20262 min read

road extension blueprint - illustration, Jake Team LLC

Heritage Ranch Trail stops at Parker Elementary School today. A contract on Monday's City Council agenda would carry it the rest of the way to FM 1417.

The council is set to consider Resolution No. 7691 on Monday, Nov. 2, awarding the Heritage Ranch Public Improvements Phase 2 project to Lynn Vessels Construction, LLC of Sherman for $3,459,996.51. The meeting begins at 5 p.m. at City Hall, 220 W. Mulberry St. The item is listed for its own vote rather than on the consent agenda.

What would be built

According to a staff report from Director of Engineering Wayne Lee, the city designed the extension under agreements with the Heritage Ranch planned development and Sherman ISD. The goal is a second way in and out for the school and for future development inside Heritage Ranch.

The new section would be a four-lane divided collector road running from the current dead end at the school to FM 1417. The project is listed in the city's capital improvement program as No. 26-032.

The bids

The city opened bids on Sept. 15, and 12 contractors responded. Staff scored the bids on price, which carried up to 70 points, along with contractor qualifications, safety record and construction time.

Lynn Vessels posted both the lowest price and the shortest schedule, the report says, and finished first with 95.9 of a possible 100 points. Its bid calls for substantial completion in 160 calendar days and final completion in 190.

The bid tabulation in the agenda packet put the engineer's estimate for the job at $4.5 million to $5.5 million. The highest of the 12 prices was just over $7 million. A'Lure General Contractors and Civil Constructors ranked second and third, at roughly $3.98 million and $4.06 million.

Staff recommend awarding the contract to Lynn Vessels and authorizing the city manager to sign it.

Also on the agenda

Among routine items, the council will consider buying a Type 1 Frazer ambulance for the Sherman Fire Department for $380,381 through the H-GAC purchasing cooperative. It would replace a 2016 Ram 4500 ambulance and be paid for from the fleet replacement fund with tax notes, according to the packet.

The agenda lists the contract award, not an outcome. Results will be known after Monday's vote.

Sources

shermantx.api.civicclerk.com

shermantx.api.civicclerk.com

Advertisement

Share

Savannah Reed· AI-assisted, edited by Jake Team

Savannah Reed writes about community life, culture, and events in Sherman.

Related Stories

More in Texas