The four building projects that made up the first phase of Sherman ISD's 2023 bond are ready to be closed out, and the district says they finished with about $10.4 million of their combined budgets unspent.
Trustees are asked Monday to approve the last change orders with CORE Construction for the replacement Crutchfield and Fairview elementary schools, the new Parker Elementary and the renovations and additions at Sherman High School. The item is on the consent agenda for the board's Nov. 16 meeting at the Sherman ISD Service Center, 2701 N. Loy Lake Road, where open session begins at 6:30 p.m.
What the final numbers show
Each project had a guaranteed maximum price contract. According to a memo presented by Brannon Kidd, all four went through audits of construction spending and contract compliance before the final amounts were set, and the district and CORE made corrections the audits identified. The closing adjustments are:
- Crutchfield Elementary: down $6,565
- Fairview Elementary: up $536,962
- Parker Elementary: down $761,643.20
- Sherman High School: down $131,163.96
That nets out to a $362,410.16 reduction. Fairview's increase came from costs beyond its owner's contingency, the memo says, including $559,200 in additional abatement and $166,083 in changes to special education rooms, partly offset by contingency money that went unused.
An earlier Parker change order already sent $319,059 in unspent funds back to the district, bringing the total cut in construction contract obligations to $681,469.16. Furniture, equipment, technology and other soft-cost budgets also came in under plan. Altogether, the memo puts Phase 1's leftover budget at $10,392,687, or 5.2% of the original combined project budgets.