Sherman ISD's first wave of 2023 bond schools closes out with $10.4 million left over

Final change orders for Crutchfield, Fairview, Parker and the high school go to trustees Monday. Audits trimmed the contracts by a net $362,410, though Fairview ran $536,962 over.

Delia Montoya· AI-assisted, edited by Jake Team

November 14, 20262 min read

School Bond Completion - illustration, Jake Team LLC

The four building projects that made up the first phase of Sherman ISD's 2023 bond are ready to be closed out, and the district says they finished with about $10.4 million of their combined budgets unspent.

Trustees are asked Monday to approve the last change orders with CORE Construction for the replacement Crutchfield and Fairview elementary schools, the new Parker Elementary and the renovations and additions at Sherman High School. The item is on the consent agenda for the board's Nov. 16 meeting at the Sherman ISD Service Center, 2701 N. Loy Lake Road, where open session begins at 6:30 p.m.

What the final numbers show

Each project had a guaranteed maximum price contract. According to a memo presented by Brannon Kidd, all four went through audits of construction spending and contract compliance before the final amounts were set, and the district and CORE made corrections the audits identified. The closing adjustments are:

  • Crutchfield Elementary: down $6,565
  • Fairview Elementary: up $536,962
  • Parker Elementary: down $761,643.20
  • Sherman High School: down $131,163.96

That nets out to a $362,410.16 reduction. Fairview's increase came from costs beyond its owner's contingency, the memo says, including $559,200 in additional abatement and $166,083 in changes to special education rooms, partly offset by contingency money that went unused.

An earlier Parker change order already sent $319,059 in unspent funds back to the district, bringing the total cut in construction contract obligations to $681,469.16. Furniture, equipment, technology and other soft-cost budgets also came in under plan. Altogether, the memo puts Phase 1's leftover budget at $10,392,687, or 5.2% of the original combined project budgets.

Security additions and school ratings

A separate consent item would spend $26,220.46 in 2023 security and technology bond money on more card readers and door sensors, plus video intercoms inside the security vestibules at Crutchfield, Fairview and Parker. A staff memo says those three campuses now have no way for a visitor standing in the vestibule to talk with the front desk.

Before the regular session, trustees hold a 5 p.m. workshop that includes a public hearing on targeted improvement plans the state requires for Crutchfield, Neblett and Parker. A district presentation says Crutchfield received an F, scored 52, in 2026. Parker (F, 59) and Neblett (F, 54) both failed in 2025 and rose to C ratings of 79 and 75 this year.

The plans are due to the Texas Education Agency by Nov. 20, and the district's stated goal is a C or better at all three in 2027.

Sources

shermanisd.diligent.community

shermanisd.diligent.community

shermanisd.diligent.community

shermanisd.diligent.community

Advertisement

Share

Delia Montoya· AI-assisted, edited by Jake Team

Delia Montoya reports on schools and higher education across the Sherman area.

Related Stories

More in Texas